en REFERENCES
Studies















 
Study of cogeneration plant Kroměříž - CZ - 1 x 32 MW gas turbine, 15 MW steam turbine
  • Feasibility study
  • Zoning permit documentation
  • Bidding documentation


Power generating units with desalination
  • Steam boiler 2 x 1600 t/h
  • Steam turbine 2 x 330 MW
  • Desalination 270.000 m3/day


Combined cycle units with desalination
  • Gas turbine 4 x 240 MW
  • HRSG 4 x 360 t/h
  • Steam turbine 4 x 60MW
  • Desalination 270.000 m3/day


Power plant Mělník III, Czech Republic.
Replacement of unit no. 7 – 110 MW by a cogeneration unit 1 x 236 MW.

Cogeneration plant Trmice. Reconstruction to cogeneration plant burning gas.

Cogeneration plant Michle, Prague, Czech Republic.
Reconstruction to cogeneration plant burning gas

Technical-economic study for reconstruction of cogeneration plant Holešovice, Prague, Czech Republic

Chemopetrol Litvínov, Czech Republic. Feasibility study of unit 1x70 MW

Energocentum Kladno, Czech Republic
Feasibility study of units 2 x 135 MW + 1 x 70 MW

Cogeneration plant Plzeň, Czech Republic
Feasibility study of unit 1 x 65 MW

Due Diligence for Energocentrum SEPAP Štětí

Cogeneration plant Gemec, Czech Republic Feasibility study of unit 1 x 6,2 MW.

Due Diligence for cogeneration plant Trmice

Cooperation in the preparation of Due Diligence for company ČEZ a.s.

Power plant Hodonín - ČEZ, a.s. - Erection of circulating cooling water system,

AES Bohemia spol. s r.o - Determination of residual service life of boiler K1, Sezimovo Ústí